Slide 1 of 7 · Settling starter · Drama · Year 8
3 minutesAlgorithm for a stage change: 4 crew, 90 seconds of blackout
You have a worksheet with a brief, 2 set lists and the rules. Scene 1 is Nan’s kitchen, Scene 2 is a hospital waiting room, and the blackout between them is 90 seconds. Today you write the algorithm for 4 crew to strike the kitchen and set the waiting room, then a partner runs it step by step to see if it breaks.
While the register is called: write your name, class and date on your worksheet, then read The brief and its 4 rules.
Starter question: Which rule means the vending-machine flat cannot come on straight away?
Slide 2 of 7 · Today’s brief and key words · Drama · Year 8
3 minutesYour brief: work out what depends on what, run jobs in parallel, test it
A scene change is an algorithm: instructions, in order, carried out by 4 people at once, that must finish inside a fixed time. You will circle the 2-person jobs, work out the dependencies, fill the timing table with a column per crew member, write an IF for the table legs and a REPEAT for the chairs, then swap and dry-run a partner’s plan.
Dependency
A job that cannot start until another job has finished. The noticeboard hangs on the flat, so the flat must be standing first.
Parallel
Jobs happening at the same time on different crew. 4 crew working at once finish far sooner than 1 person doing every job in turn.
IF and REPEAT
IF gives an instruction for each of 2 outcomes (the table clears the door, or it does not). REPEAT writes an instruction once and runs it for every chair.
Slide 3 of 7 · Steps 1 and 2: 2-person jobs and dependencies · Drama · Year 8
11 minutesStep 1 & Step 2: circle the 2-person jobs, then write what each setting job waits for
Step 1 (4 min): read the brief and both lists. Circle every job that needs 2 people. Step 2 (7 min): next to each job on the setting list, write what must be struck or set first. Copy the first dependency from the board.
| Setting job | What must happen first |
|---|---|
| Vending-machine flat (2 people, 20 s) | It stands where the kitchen table was, so the table must be struck before the flat comes on. |
Slide 4 of 7 · Step 3: the timing table · Drama · Year 8
14 minutesStep 3: fill the timing table, one column per crew member
Write start and finish seconds for every job in the columns for Crew A, B, C and D. Obey the door rule (no more than 2 in the upstage doorway) and the dependencies from Step 2. Copy the first row from the board, then plan the rest. Finish with the total time and the seconds to spare out of 90.
| Seconds | Crew A | Crew B | Crew C | Crew D |
|---|---|---|---|---|
| 0 to 8 | Table off, with B (upstage door) | Table off, with A | Kitchen chairs off, stage right | Kitchen props into the box |
Slide 5 of 7 · Steps 4, 5 and 6: IF, REPEAT, dry run, one fix · Drama · Year 8
13 minutesStep 4, Step 5 & Step 6: write your IF and REPEAT, then let a partner break it
Step 4 (5 min): write your IF statement for the table legs and your REPEAT statement for the chairs in the 2 boxes. Step 5 (6 min): swap with a partner. Read their algorithm aloud one step at a time and fill their dry-run table: Works? If it breaks, what breaks. Step 6 (2 min): take your sheet back and write the one change you would make.
IF model: IF the table clears the upstage doorway THEN carry it straight off (12 s) ELSE fold the legs first (+10 s), then carry it off.
REPEAT model: REPEAT FOR EACH of the 3 chairs in stack 1: line it up with its tape mark (2 s each).
Slide 6 of 7 · Self and partner check · Drama · Year 8
3 minutesCheck your algorithm against the success criteria
Tick each criterion your work meets. Your partner then checks your IF: does it give an instruction for both outcomes?
- I broke the change down into jobs and worked out which ones depend on another job finishing first.
- I used the 4 crew in parallel, so my total time is much less than the 116 seconds of work.
- I handle the table-leg problem with an IF, giving an instruction for both outcomes.
- I used a REPEAT for the chairs rather than writing the same instruction out 6 times.
- I tested my algorithm by having somebody else follow it exactly, and I recorded what they found.
Slide 7 of 7 · Plenary review · Drama · Year 8
3 minutesRound the room, then quick-check answers before handing in
Everyone says their total time in seconds and names 1 job they ran in parallel. Then check these answers.
| Question | Correct answer |
|---|---|
| How many seconds of work are there in total, and how fast can 4 crew do it? | 116 seconds of work, done in 55 seconds in the worked example, 35 to spare out of 90. |
| What is the longest chain that limits the change? | Table, then flat, then noticeboard. Each must finish before the next can start. |
| What is the worst case if the table legs have to be folded? | 65 seconds: every A and B job shifts by 10 s. Still 25 seconds to spare. |